Construction Draw Schedule Visualizer

See how a fixed-price contract is paid: 10% at contract, then five progress draws.

Due at Contract

$200,000

Permit
$200,000
Excavation
$300,000
Mechanical Rough-In
$500,000
Framing
$500,000
Final Occupancy
$300,000

Draw timeline (about 16-22 months)

ContractOccupancy

Illustrative percentages; your contract sets the schedule. Lender draws and Construction Act holdbacks may apply.